LANDSIDE






OTHER FACTS
& INFORMATION





|
St.
Louis Downtown Airport's
New Air Traffic Control
Tower

  
 
MILESTONES:
-
September 2005:
Award Construction Contract
-
October
31, 2005: Construction Ground Breaking
-
June
2006 : Significant Constrution Begins
-
Fall
2007: Equipping and training begin
- Spring 2008: Certified Operational
-
Summer
2008: Demolition of Existing Tower
PHASE ONE of a three-phased
program to construct a new air traffic control tower at St. Louis Downtown
Airport was completed November 26, 2001 with the selection of the new
tower site, depicted in the aerial photo, above.
The site selection ended a six-month effort that studied eight potential
sites before selecting the best one. The site selection team included
local air traffic controllers and airport management as well as a team
of engineers from FAA Headquarters and the independent architectural and
engineering firm of R. W. Armstrong.
The site selection process included an investigation of the topography
and environmental considerations for each potential site, the surrounding
environment (trees, homes, distracting lights, sun angles, etc.), viewing
angles, effects on approach minimums, and a variety of other criteria.
A variety of evaluation techniques were used including engineering analysis,
viewing airport traffic from lifts and cranes from each of the finalist
locations, and finally, a traffic simulation in the FAA's control tower
simulator located at the FAA Technical Center in Atlantic City, New Jersey.
PHASE TWO of the project, the design
phase, began January 2003 and was substantially completed in September
2004. Although the FAA has several standard tower designs based
on the type of airport and volume of traffic, the applicable standard
design must be modified to fit our exact needs and location requirements.
Review and fine-tuning of the design has continued and reached the 100
percent design level in January 2005.
Once completed, the new $7
million tower will be 138 feet tall, complete
with elevator, and will provide the controllers an approximate eye height
of 113 feet, a 70 foot increase over the viewing height from our existing
tower. The tower will have its own access road coming directly off
Jerome Lane eliminating the traffic in the subdivision as the controllers
drive to and from work. The construction will also include a 5,000
square foot support building at the base of the tower to house tower administrative
personnel, a back-up generator power source, and other support equipment.
The existing tower was built in 1973 and was later
expanded by adding a mobile office trailer adjacent to it to house the
tower's administrative function. Airport traffic has grown steadily
since the tower was built and the need for space has outgrown the capacity
of the small, outdated tower.
PHASE THREE, the construction phase,
began in June 2006. Although scheduled to begin in Fall of 2005, contractual
problems delayed the start of construction. A new construction contract
was awarded to Plocher Construction
Company, Inc., of Highland, Illinois in April 2006 and substantial
construction began. Construction of Molla Drive was completed in July
2006 (except for final paving) and the tower cab was raised to the top
of the shaft in mid-December 2006. Construction was substantially complete
in Fall 2007 and the FAA accepted the facility and began installing the
communications equipment and furnishings in December 2007.
Completed and Operational:
June 26, 2008
GO BACK TO THE CONSTRUCTION PAGE
|